Sabetta Port Project Progresses According To Schedule
Federal facilities of Sabetta Port, being built under the Yamal-LNG project, will be finished in line with the schedule, said Artem Melnikov, Director of Fertoing Ltd., one of the project contractors, at the 3rd International Forum of Dredging Companies.
The international dredging conference, organized by Media Group PortNews, held yesterday in Moscow.
According to Alexander Ivanyuk, Technical Director of Mordraga LLC, DEME’s Russian subsidiary, and the company in charge of Sabetta dredging, the year of 2016 is to see dredging at the port’s water area up to -15.2 meters and at the access channel up to -15.1 meters.
The accomplishment of the second phase of the sea channel (up to 495 meters wide) and the access channel (up to 295 meters wide) is scheduled for 2017, Ivanyuk added.
Total amount of dredging works at Sabetta Port for the 2014-2017 period will contain a removal of 68.6 mln cbm of material.