Dredging of Housatonic River Will Start This Fall

The U.S. Army Corps of Engineers, New England District, awarded the $9.3 million contract to Cashman Dredging and Marine Contracting Company of Quincy, Mass. The work will be performed over a three to four months between Oct. 1 and Jan. 31, 2018, for shoals inside Milford Point, and between Oct. 1 and Feb. 28 for shoals seaward of Milford Point.

The last dredging of the Housatonic was in November 2012 when the Corps’ dredge Currituck removed about 50,000 yards of shoal material. This project will take nearly 300,000 cubic yards(a cubic yard of sand weighs nearly three tons) of clean, fine sand from the Housatonic’s shallow navigation channel and move it to Connecticut’s premier beachfront park, Hammonasset Beach State Park in Madison.

The sand will be transported by barge to re-nourish the eroding beach at Hammonasset and this will really improve the beach up at Hammonasset. The Connecticut Port Authority has followed through with the finding for this project.

The news is collated by Globaldredge.com – Dredging Pipeline Supplier.

Port of Veracruz Dredging Contract

Jan De Nul Group, a dredging company, won a contract for deepening the Port of Veracruz. The contract value is about 60 million euros (the U.S. $65.5 million).

The contract includes dredging of the access channel and the turning basin, and in total, 13 million cubic meters will be removed and reclaimed. On top of the reclaimed areas, five new port terminals will be built, which will be able to handle up to 100 million metric tons per year.

The works are scheduled to commence in the summer and will be completed in March 2018.

The news is collated by Globaldredge.com – Dredging Pipeline Supplier

Poole Harbour Expansion Project

Jenkins Marine has been assisting BAM Nuttall with the new £10 million quayside construction development in Poole harbor (the South Quay Project).

The new quay will need approximately 1,800 tons of steel piles, all of which will be delivered by sea. Jenkins Marine is also providing assistance with demolition work for existing structures, dredging, and additional piling barges.

The project, which is due for completion by the end of 2017, will ensure that the Port remains competitive with facilities that can accommodate a much wider range of shipping and marine activities.

The expansion of the port will be able to accommodate vessels up to 220m long in a variety of different sectors including yacht transportation, bulk cargo, short sea containers and project cargo.

The news is collated by Globaldredge.com – Dredging Pipeline Supplier

Maintenance Dredging Project of Cargo terminal

Port of Port Angeles plans to pursue an estimated $700,000 berth maintenance dredging project for its cargo terminal, Terminal 3.

The work is planned to dredge about 6,300 cubic yards of material from the berth area, bringing the seafloor to about 45 feet below sea level.

The pier is used by two companies to transport debarked logs from the Olympic Peninsula to markets in China.

Last year, 15 cargo vessels were loaded at the pier and transported 84 million board feet of logs overseas, providing $2.35 million in revenue for dockage, wharfage, and service.

There are two options for what to do with the dredged material, ranging from disposing of the sediment in the water to disposing of it upland.

One option would have dredged material placed on port property. The other upland option, estimated to cost $2.5 million, would have had the sediment disposed of at a landfill in Eastern Washington or Oregon.

It was estimated the project would take about two weeks and that permitting for the project will take about eight months.

The news is collated by Globaldredge.com – Dredging Pipeline Supplier

Maintenance Dredging Project at Port of Cape Town

Transnet National Ports Authority (TNPA)’s Dredging Services division has embarked on a $ 1.1 million maintenance dredging campaign at the Port of Cape Town to restore the design depths inside Duncan dock.

The maintenance dredging work, which began on March 8, 2017, is scheduled for completion by the end of April 2017. The main objective of the dredging work is to ensure the Port of Cape Town provides safe navigational channels and berthing facilities for shipping by restoring the original design depths.

Two dredging vessels, the Isandlwana, a Trailing Suction Hopper Dredger, and the Italeni Grab Hopper Dredger have been mobilized by TNPA Dredging Services for this purpose.

The Isandlwana, which has a 4,200 m³ hopper capacity, will remove approximately 70,000 m³ of material from the sea bed before the end of April. Spoil is pumped into the hopper and can be offloaded by discharging through 10 conical bottom valves. Pumping ashore is also possible by means of either a floating pipeline, a side discharge mechanism or by ‘rainbowing’, where the dredging vessel discharges material that has been claimed from the ocean floor in a high arc to build a landmass elsewhere, such as during nourishment of beaches, to prevent erosion along the coasts or to reclaim land.

TNPA’s fleet renewal program has boosted the dredging division’s capacity to aid the removal of approximately four million cubic meters of excess material from the seabed every year at South Africa’s ports.

The news is collated by Globaldredge.com – Dredging Pipeline Supplier

Maintenance Dredging of Kennebec River

Solicitation Number: W912WJ-17-B-0005

Notice Type: Solicitation

Work Description:
The work involves urgently needed dredging of two portions of the authorized, 27-foot deep, 500-foot wide FNP in the lower Kennebec River. Dredging would restore the channel to its authorized dimensions and involves removal of a total of about 70,000 cubic yards (cy) of clean sand. Approximately 50,000 cy of material will be removed from the Doubling Point area (i.e. just below Bath) and approximately 20,000 cy of material will be removed from the Popham Beach area (at the river mouth). The 50,000 cy to be removed from the channel at Doubling Point includes approximately 35,000 cy of advance maintenance dredging. Material dredged from the Doubling Point area will be placed in the previously used in-river disposal area north of Bluff Head in about 95-100 feet of water. Material dredged from the Popham Beach area will be placed in the previously used 500-yard diameter nearshore disposal area located about 0.4 nautical miles south of Jackknife Ledge and in about 40-50 feet of water.

Posted Date: March 29, 2017

Due Date: N/A

Nation: USA

Contracting Office Address:
696 Virginia Road
Concord, Massachusetts 01742-2751
United States

Primary Point of Contact.:
Julio Hall,
CONTRACT SPECIALIST
Julio.E.Hall@usace.army.mil
Phone: 9783188035

The tender information is collated by Globaldredge.com – Dredging Pipeline Supplier