RDA Contracting Secures a construction contract

US Army Corps of Engineers, Sacramento District, recently has awarded a $2.16 million construction contract to RDA Contracting for erosion repair near Isleton on the Sacramento River.

The work involves placing about 14 tons of quarry stone along 591ft of the eroded levee. The construction work is planned to start in August and is expected to complete by the end of 2016.

The construction work is critical for public safety and can prevent property damage. The eroded levee could be destroyed in flood season, endangering public safety. So Corp Project Manager has expedited the contract award.

The work will also improve California Highway 160 adjacent to the river from Sacramento to Antioch after the erosion repair work is completed. As part of the ongoing Sacramento River Bank Protection Project, the work will repair river bank erosion and protect levees along the Sacramento River and its tributaries to reduce flood risk for the Central.

The news is collated by Globaldredge.com – Dredging Pipeline Supplier Valley.

A dredging contract in Mianus River

A contract for the dredging of the clogged Mianus River channel in Greenwich town is being signed.

The work includes dredging about 50,000 cubic yards of sediment from the federal channel, which has not been dredged in more than 30 years. The project must be carried out between Oct. 1 and Jan. 31 owing to environmental conditions.

The river was last dredged in 1985 which removed 53,000 cubic yards of sediment. In recent years, much silt has built up, the channel is barely passable in sections at low tide, and boats with a big draft in the water would be hitting the bottom. So the Army Corps of Engineers plans to dredge the Mianus River so that those boats can’t dock there.

The project will restore the channel to its dimensions of 6 feet deep and 100 feet wide, running from Cos Cob Harbor up the Mianus River to about 400 feet downstream of the Boston Post Road Bridge. After this dredging, the channel would be 75 feet wide. The sediment will be placed in the Western Long Island Sound Disposal Site.

The news is collated by Globaldredge.com – Dredging Pipeline Supplier

Barnstable Attempts to Modify Harbor Entrance Channel Dredging Project

The army corps of engineers is accepting public comment on a proposal that modify the dredging project of the mid-entrance channel in Barnstable Harbour.

Barnstable is looking to dispose of about 3,500 cubic yards of sediment at the Cape Cod Bay Disposal Site instead of putting dredged material in a viable spot Blish Point Sediment Containment Basin.

The dredging project aims to dredge a 182,000 square-foot area to a depth of 6 feet below mean low water at Maraspin Creek/Barnstable Harbor. About 20,000 cubic yards of sandy material will be removed and dewatered above the high tide line at Millway Beach before it be placed as beach and dune nourishment at the Sandy Neck Cottage and Lighthouse areas. Work will be operated in the fall or winter.

Public comment will be accepted through August 18, and their comment should be submitted to the U.S. Army Corps of Engineers, New England District, Regulatory Division (ATTN: Kevin Kotelly), 696 Virginia Road, Concord, MA 01742-2751.

The news is collated by Globaldredge.com – Dredging Pipeline Supplier

Oceanside Harbour Dredging Projects

Dredging operations in the Oceanside Harbour are in progress. The work includes removing the 30,750 cubic yards of material from the Harbour’s entrance channels.

CJW Construction of San Diego (CA), the contractor of the dredging projects, has so far dredged about 68,800 cubic yards of sand. The designated dredging material is 260,000 cubic yards of sand. The dredged material is currently being placed along Oceanside’s beach.

Oceanside Harbour is one of four annual dredging projects conducted by the USACE’s Los Angeles District to maintain the federal channels at an authorized federal depth of -25 feet.

The projects are expected to be completed on July 27. According to the contractor, CJW will extend the pipe south an additional 1,000 feet to place material near the pier and lifeguard headquarters.

The news is collated by Globaldredge.com – Dredging Pipeline Supplier

Great Lakes wins dredging nets contracts worth $93 million, plus $6 million in options

OAK BROOK — Great Lakes Dredge & Dock Corp. was recently awarded four contracts value $93 million.

The first award is a $30 million contract for coastal protection work that includes sand replenishment and dune building from Kismet to Seaview on Fire Island, New York. Approximately 1.3 million cubic yards of sand will be dredged and pumped onto the beach. The work is scheduled to complete by December 2016.

The second award is a $29 million contract that includes pumping an additional 1.8 million cubic yards of sand from Barnegat Inlet to Little Egg Inlet on Long Beach Island in New Jersey. Work is expected to be completed in the spring of 2017.

The third award is a $14 million Duval County Shore Protection construction contract that includes placing 650,000 cubic yards of sand on approximately seven miles of eroded beaches in Florida. Work is scheduled to be completed by year’s end.

The fourth award is a $12 million contract that includes pumping approximately 1.7 million cubic yards of sand to reconstruct the beach and build dunes to protect infrastructure. Work is expected to be completed by the end of the first quarter of 2017.

Besides, the company was awarded a $7.9 million base contract with a potential $6.1 million option for rental work on the Mississippi River. If awarded, the dredging work will start next summer.

The news is collated by Globaldredge.com – Dredging Pipeline Supplier

Cedar River dredging and flood-control project

Renton undertakes a big dredging project on the Cedar River in food prevention. The overall project estimated to cost over $13 million funded by The King County Flood Control District. Besides, it’s also providing $7.5 million to fund the construction portion of the work.

The project includes to dredge more than 120,000 cubic yards of gravel and sediment from a 1.25 mile stretch of the rive. Besides, unstable banks will be repaired, outfall from storm pipes will be improved, vegetation will be replanted and invasive vegetation next to a levee and floodwall will be removed. The dredging operation starts from Lake Washington to the Williams Street Bridge.

The project could help protect homes, roads and bridges from major flooding this winter. It also reduces the risk of flooding to private, public and commercial properties.

The major dredging work will be finished in August when the river level is at its lowest. Other restoration work is expected to continue through November.

The news is collated by Globaldredge.com – Dredging Pipeline Supplier