Kansas Water Office Efforts Recognized By U.S. Army Corps

 

The Kansas Water Office (KWO) was recognized recently by the U. S. Army Corps of Engineers (USACE) for their continued partnership and contribution to the USACE mission during the approval process of the John Redmond Reservoir Dredging Initiative.

This project is the first and largest inland Section 408 request -permission for the alteration of a USACE civil works project- in the nation to be approved by USACE, Headquarters.

Lieutenant Gen. Thomas P. Bostick, the U.S. Army Corps of Engineers Commander, and Col. Richard A. Pratt, Tulsa District, Commander, presented the award to the KWO as well as former KWO employee, Susan Metzger, noting the efforts by the office reflect highly upon the state of Kansas and the nation.

“The KWO’s commitment to delivering enduring and essential water resources solutions to our nation through successful completion of all needed elements for review and approval of the John Redmond Dredging Initiative was commendable,” Gen. Bostick said.

“Ms. Metzger’s demonstration of expert-level knowledge and skills in managing the drafting of technical elements of the Programmatic Environmental Impact Statement, was pivotal for the successful completion of this effort by KWO.”

Since 1964, John Redmond has lost an estimated 42 percent of its conservation pool storage capacity, 80 percent more than originally projected by the USACE at the time the reservoir was completed.

While there have been many short and midterm alternatives to reduce sediment or increase storage through streambank restoration projects and a two-foot pool raise and reallocation, these efforts alone will not remedy the sedimentation rate alone.

“Our work to dredge John Redmond Reservoir is part of our effort to preserve and extend water resources in Kansas,” said Governor Sam Brownback. “Increasing its storage capacity is an important part of our vision to preserve water resources in Kansas. I commend the efforts in protecting this vital resource.”

Dredging sediment from the conservation pool would restore water supply storage for the benefit of the regional water users and restore the lost aquatic habitat for the benefit of public recreation and the lake ecosystem.

The first dirt work began in November 2015 and the official dredging will start this spring.

First Phase Of Cocoa Beach Dredging Underway

The City of Cocoa Beach, in conjunction with Brevard County, has begun the first phase of the Cocoa Beach dredging project.

This phase contains areas in the canal between Jack Drive and Kent Dr., according to the Cocoa Beach Public Works’ announcement.

Central Sand, Inc., the contractor, estimates that it will take four to six weeks to complete dredging in this area.

During the project, Central Sand will dredge 83,000 cubic yards of material from the city canals, placing the spoil on 10 acres of city-owned land just north of Brightwaters Drive.

The dredging will be done Mondays through Fridays from approximately 8:00 am to 5:00 pm, according to Brevard County Natural Resources Management Department.

The canals will be closed to boat traffic during dredging and remain open on weekends.

Royal Smals About To Complete Solingen Dredging Project

Royal Smals is putting finishing touches to the Sengbachtalsperre dredging project, Which is a water reservoir in the Wupper catchment basin that is used by Stadtwerke Solingen to provide drinking water for the city.

The Sengbachtalsperre As one of the oldest drinking water reservoirs in Germany, the Sengbachtalsperre holds 2.8 million cubic meters of water. Upstream of the Sengbachtalsperre dam is a smaller reservoir that has been built to prevent settling of sediments from the feeder streams to the main reservoir.

In the past two years, the water quality in this smaller reservoir has been negatively influenced by planktothrix rubescens, a form of blue algae, up to the point where the utility even had to temporarily halt the intake of drinking water.

Stadtwerke Solingen as principal issued a tender for removing 26,000 cubic meters of sediment and pumping it to a bund in order to prevent the formation of blue algae in the future.

Royal Smals submitted a bid and has subsequently been appointed contractor for this dredging project. The 8″ cutter suction dredger Pollux is now being used for the work.

According to the Dutch Water Sector, Royal Smals expects to complete the dredging project this spring.

Duck Key Canal Restoration Project On The Table

The Monroe County Commissioners will meet on Wednesday, January 20th, at 9 AM at the Marathon Government Center to talk about a proposal from Duck Key residents to relax some county rules on canal maintenance dredging.

The commissioners will review a document called Duck Key Canal Restoration which identifies eight areas that have silted up to less than 5ft of depth at low tide.

According to the residents, no appreciable maintenance has been performed since the construction of the canals 60+ years ago.

The residents, represented by Ms. Popham, have asked the commissioners to consider modifying the current county prohibitions (i.e. allow maintenance dredging where there are seagrasses and hardbottom communities) that prevent the restoration of the canals.

After reviewing various governmental agency requirements, Duck Key residents believe that the requirements of the state and federal agencies can be met but cannot move forward with the project because of the county’s prohibition on maintenance dredging.

Hilo Harbor Pier 4 Project Includes Dredging

HDOT-the Hawaii Department of Transportation, Harbors Division, celebrated last Friday, January 15, the Pier 4 Project at Hilo Harbor with a groundbreaking and dedication/blessing ceremony.

The project includes multiple phases: dredging and construction of the Pier 4 Inter-Island Cargo Terminal, construction of the Inter-Island Cargo Terminal Facility–Container Yard, and Kumau Street Entrance Improvements.

HDOT will start work on the final phase of the project, the Pier 4 Inter-Island Cargo Terminal. This phase involves the creation of a 602 linear foot reinforced concrete pier with associated site work that will be located to the west of the existing Pier 3.

The finished Inter-Island Cargo Terminal Facility–Container Yard component of the project reconstructed a portion of the existing container yard and built a new adjacent container yard with a comfort station, lighting, and utilities. This phase generated an additional 4 acres to be used for cargo operations, amounting to approximately 10 acres total.

“The construction of Pier 4 at Hilo Harbor will create a dedicated operating area for inter-island cargo operations which will relieve the issues that the harbor currently experiences,” said HDOT Director Ford Fuchigami. “Transporting provisions to Hawaii County will become more efficient, thus promoting economic and social growth.”

The estimated total cost for the project is $68.5 million. Work on the final phase is anticipated to be completed by July of 2017.

Royal IHC Completes Lift And Integration Of Deckhouse

Royal IHC has just published a video of placing the deckhouse on IHC-built trailing suction hopper dredger Jun Yang 1.

The 21,028m³ TSHD, being built for CCCC Guangzhou Dredging Co., was launched on Saturday, 19 December 2015, at IHC’s shipyard in Kinderdijk, the Netherlands.

When delivered, the vessel will be the largest of its kind in China, enabling GDC to carry out capital dredging and land reclamation jobs on the international market in an efficient way.

The JUN YANG 1, scheduled for completion by the end of July 2016, is the 19th vessel built by IHC for GDC over the last 40 years.