Everything is ready for Lake Cathie Dredging
It is reported that a dredger has arrived at Lake Cathie and will be moved into position over the coming days, Port Macquarie-Hastings Council said in their latest release.
Approximately 21,000 cubic meters of sand will be dredged, and relocated to the edge of Foreshore Reserve to reclaim open space that has been lost to erosion in recent years.Sand will also be relocated for beach replenishment along approximately 400m of the beach, fronting Illaroo Rd, the council said.
It is significant to conduct this dredging .Dredging operations, to be conducted by National Dredging Solutions, are expected to take approximately 7 weeks to complete (weather permitting).Dredging operations are expected to start on Monday, 21 May.