The dredging of this project mainly includes the dredging of the connecting water area and the port basin. The total dredging area is 1.27 million square meters, and the dredging engineering volume is about 9.8 million cubic meters. The dredging soil is silt and silty clay.
The project will dredge an “exclusive lane” for super-large LNG ships entering and leaving the port, further improving the utilization rate of the sea channel and ensuring the safe production and development of the port.
At present, the monthly average dredging volume of the project exceeds 1 million cubic meters. According to the current construction progress, the dredging project is expected to It will be fully completed by the end of August.